Defuelling at the UK’s Chapelcross magnox reactor has begun on its reactor 3. Through the end of August 2009, the 18 flasks of fuel, containing nearly 2,500 fuel elements already despatched to Sellafield for reprocessing have all came from Reactor 1.
The defuelling of Chapelcross is a major decommissioning project for the site. From April 2009 to November 2011, between 270-300 flasks will transport all 38,075 fuel elements removed from the four reactors at Chapelcross for reprocessing at Sellafield.
Tim Dunham, Chapelcross Defuelling and Operations Manager said : “Since April we have averaged nearly a flask a week being transported from the site to Sellafield. What this now means is the site has two reactors to defuel in parallel, giving Chapelcross the opportunity to ship up to two flasks a week, subject to flask availability.”
Related ArticlesTemelin’s hard-earned success 2,300MW on the line Belene moves forward In at the ground Fluor A critical end Interview: the middle link Atomstroyexport to develop Belene Wartsila returns to nuclear industry Nuclear in Eastern Europe: a lively bright spot? Skoda sale CEZ increases Skoda holding Skoda’s nuclear manufacturing arm sold New nuclear build – sufficient supply capability? RPV installed at Mochovce 4 Delay in Belene bids Doosan joins forces with Škoda Power