Windscale Pile Chimney (photo credit: Sellafield Ltd)Nuclear clean-up teams have removed the huge diffuser at the top of the Windscale Pile Chimney on the Sellafield site in the UK. 

The diffuser gave the 125-metre chimney its distinctive top-heavy appearance — a feature of the west Cumbrian landscape for nearly 70 years. The dismantling took three years and has also removed the seismic risk associated with the chimney.

“I’m delighted to have reached this point. Removing the seismic risk is a huge achievement,” said Geoff Carver, Sellafield Ltd project manager. “This is a clear demonstration of progress towards our purpose of delivering a clean and safe environment for future generations. Many people have contributed to this success. Sellafield Ltd employees have worked closely with their colleagues from our partners ADAPT, Doosan, Mammoet, KDC, Kaefer, the Design Services Alliance, and Nuvia. The work was hugely challenging and much of it took place during the COVID-19 pandemic.”

The diffuser had to be cut up in-situ, more than 100 metres above ground. Sections were then transported separately down to the ground. It required 200 moves to clear the entire block. Work is now taking place to remove a metal frame platform and reduce the access shaft. Once that work is complete, a key delivery milestone will be met. Following this, work will start on demolishing the chimney barrel.  

Removal of the diffuser and the progress made on the demolition represents an important achievement for the Nuclear Decommissioning Authority’s (NDA) mission to clean-up the UK’s earliest nuclear sites. NDA CEO David Peattie said: “In reaching this significant milestone of removing the Windscale Pile Chimney diffuser, we take another step forward in our clean-up mission.

Demolition work started in December 2018. The first block was removed from the diffuser in January 2019. A total of 226 blocks have been removed from the top of the chimney stack, each weighing 2- 9 tonnes. The total weight of all 226 blocks is 1232 tonnes. This has reduced the height of the stack by 15.42 metres. The demolition was delivered by a team of 54, including 39 from ADAPT and their subcontractors and 15 people from Sellafield Ltd.

 The sections of the diffuser structure have been cut by machine using diamond wire saws. These cut blocks were removed from the top of the stack and lowered into the controlled area canopies ground using the tower crane. The blocks were then remediated and transferred to the bagging station on the Sellafield site where a Goliath crane was used to manoeuvre the blocks ready for transport to interim storage prior to disposal.

This was either to the Calder Landfill Extension Segregated Area on the Sellafield site, or Low Level Waste Repository, dependent on contamination levels and conditions for acceptance at each location.

The team also introduced a fit for purpose facility to diamond wire cut the face of some of the removed contaminated blocks to ensure we manage the blocks in accordance with the waste disposal hierarchy.


Photo: Dismantling of the diffuser has now been successfully complete (Credit: Sellafield Ltd)