Building a CANDU future

20 June 2018



In Ontario, Canada, more than 60% of the electricity used in 2017 was produced with nuclear power. With successful completion of two huge refurbishment projects, the province can expect four more decades of power from nuclear, Jacquie Hoornweg reports.


TOPPING THE LIST ON CANADA’S Top 100 infrastructure projects for 2017 are two energy projects. This is not surprising in a country known for its oil and gas resources and its large hydro infrastructure. But the projects are neither fossil nor water. They are nuclear refurbishments by Canada’s largest province, Ontario, home to 13.6 million people. The projects are part of the provincial government’s commitment to eliminate coal use (the province achieved its coal-free goal in 2014) and move to a long-term clean energy mix. In Ontario’s most recent long-term energy plan, the province’s clean energy future is built on a baseload supply of nuclear at least into the early-2060s, just as it has been for the past four decades.

The projects

The first refurbishment project is at Ontario Power Generation’s Darlington plant, a four-unit 3500MW station, which is now in execution on its first unit. It is followed closely, with some overlap of execution in the early and mid-2020s, by a life extension project starting in 2020 for six of the eight Bruce Power units at the company’s 6300MW station, which includes major component replacement. 

Bruce Power returned the first two units to service from refurbishment projects in 2012 and 2013.

Between them, the Darlington refurbishment and Bruce Power life extension account for almost $26 billion of investment until the final unit returns to service at the Bruce site in the early 2030s and then through continued life extension activities at Bruce. The economic impact of that investment is exponential, multiplied through the supply chain, employment and spin-off spending and development that is rippling through the entire economy.

Already, the effects of the combined projects are being felt in communities that house Canada’s nuclear supply chain of more than 200 largely Ontario-based companies. Along with the operators, the supply chain from the largest contractors to the smallest sub-contractors and suppliers are continuously hiring workers and procuring materials and services. In addition to supplying manpower on the project site, they are filling orders for tooling, plant equipment and components. The project has been an opportunity to enter into new advanced-technology manufacturing to meet the need for artificial intelligence and virtual reality (VR) to assist with equipment and software, for applications ranging from supplementary VR training to prepare new workers for a nuclear environment, to robotics that will execute the most invasive work in high radiation areas. For example, laser-scanning technology digitally captures exact shapes and sizes of objects and spaces allowing for replication for tool testing and training. The images are then displayed in a 3D format workers and designers can access through virtual reality holographic headsets that immerse users into the plant environment allowing scenarios and task sequences to be played and replayed without the cost and safety constraints of real-reactor time. Artificial intelligence is also providing interactive and responsive supplemental training for the large number of new workers being on-boarded into a nuclear environment for the first time (see also NEI December 2017, p27-29).

Ontario’s refurbishment challenge

It is estimated the projects will create about 60,000 jobs throughout the Canadian nuclear industry. This is a significant economic impact. It is also a logistical challenge. The industry needs to on-board and train numbers of workers and impart safety culture amongst people who come from a construction, project management or administrative background and, in many cases, are entering the nuclear arena for the first time.

Building on lessons from their other mega projects, the companies are taking several steps to smooth the transition from an operations mindset to a project focus including:

  • Adjusting to new demands in human performance and development and refinement of high-function project management skills;  
  • Familiarising and providing exacting standards of oversight on documentation from all project workers to ensure restart approvals go smoothly on tens of thousands of tasks, even when approvals come months after some of the tasks have been completed;
  • Training vendors throughout the supply chain on large- scale nuclear parts procurement to avoid fraudulent and counterfeit parts, which could fail or introduce cyber security risks into the plant;
  • Ensuring strong quality control for parts manufacturing and task completions. In projects the wrong work, or poor-quality parts, can have an impact far down the road and mean millions of dollars of rework; and
  • Developing a common understanding of the reactor work space, including the variables that will be encountered when taking apart a nuclear reactor that has been operating for decades and putting it back together again.

Once the utilities have done this, they must take the mega-project and complete it in an operating station where several other units continue to produce electricity alongside it. The added challenge for Bruce Power and OPG is to choreograph the human, equipment and parts resources required to complete synchronised and overlapping work across the two stations.

These challenges call for the strongest collaboration and engagement the industry has undertaken to date. Government and regulators will be watching closely each step of the way. With years of preparation already in the rearview, the operators are confident they will succeed.

An industry collaboration model

In a memorandum of understanding, Ontario Power Generation (OPG) and Bruce Power confirmed their commitment to improve their refurbishment programmes through collaboration. This included sharing lessons learned and best practices in refurbishment and operations, and coordinating efforts to reduce costs and limit execution risk. Specific initiatives include asset management and inspection programmes, procurement, tooling and replacement of major components (including de-tube, re- tube and feeder replacement work). They have collaborated on labour arrangements and logistics.

Through organisations like the CANDU Owners Group (COG), the entire CANDU industry, including other operators worldwide and the supply chain, is working to ensure success of the two projects and innovate to manage human and technical performance. Activities undertaken through COG include:

  • A refurbishment forum: allowing operators to share information, identify needs for the refurbishment projects and develop new initiatives to solve challenges.
  • Supply chain knowledge and training: COG’s supplier participant programme brings together utility and supply chain leaders to discuss challenges, expectations and potential initiatives to develop knowledge. They are building knowledge in nuclear safety, safety culture, leadership and training.
  • Return to service workshop: A recent COG three-day workshop provided an opportunity for CANDU utilities to talk about lessons learned from past projects. COG is developing an inventory of best practices and operating experience to be applied as future units come back online at Embalse, Darlington, Bruce Power and others.

Jacquie Hoornweg, Reporting for CANDU Owners Group 

CANDU
CANDU BWXT Canada Inc. is manufacturing 32 steam generators at its Cambridge facility for Bruce Power’s major component replacement
CANDU
CANDU Mike Rencheck, Bruce Power’s President and CEO announces $914 million in advanced manufacturing contracts for its major component replacement project in April 2018
CANDU A recent workshop enabled CANDU operators to share lessons from past refurbishment projects
CANDU The Darlington turbine hall. For the first time all turbine blades and rotors were removed and reinstalled to ensure continued operation for another 30 years
CANDU Turbine casings from Darlington 2 waiting for reinstallation


Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.