Korea’s Doosan Heavy has begun preliminary excavation work on Shin-Wolsong 1 and 2.
Meanwhile, having obtained the construction permit from the Ministry of Science and Technology, the initial concrete installation ceremony at Shin-Kori 2 was held on 5 June. With the concrete work now begun, Shin-Kori nuclear reactor 2 will be installed next year, says Doosan, which will supply the nuclear reactor, steam generators and other major items of equipment.
Shin-Wolsong 1 and 2 and Shin-Kori 1 and 2 are due to be completed by 2012 with Shin Wolsong Unit 1 due to see concrete pouring beginning in December and Unit 2 concrete pouring to begin in the following June. Fuel loading will begin in April 2011 and 2012 respectively before commercial operations begin in December 2010 for Unit 1 and December 2011 for Unit 2.
Concrete pouring for Unit 1 at Shni-Kori began in June last year. Fuel loading at Shin-Kori 1 & 2 will begin in June 2010 and June 2011 respectively, before commercial operations begin six months later in the December of the respective years.
Related ArticlesAlstom opens US turbine facility Enel and Rosatom sign nuclear accord Rosatom and Rusal plan nuclear metals complex