Iran’s Bushehr nuclear power plant has been connected to the national grid. It began supplying around 60 MW of its 1000 MW capacity on Saturday 3 September at 11:29pm, the Atomic Energy Organization of Iran (AEOI) said.
Construction on Bushehr by German company Siemens KWU started in 1975, but the work was stopped in 1979. Iran signed a deal with Russia in 1995, under which the plant was originally due to be finished in 1999, but the completion of the project was repeatedly delayed.
The most recent delay, in February 2011, was caused by the discovery of damaged internals of a coolant pump supplied in the 1970s. To avoid potential consequences of metal debris getting on the fuel assemblies, they were unloaded and washed, while the reactor pressure vessel was cleaned. The fuel was reloaded in April and the plant achieved criticality in May 2011.
In August 2011, the Government of Iran invited an International Atomic Energy Agency delegation to visit the country’s nuclear facilities, including nuclear power plant that has been built by Russia’s Atomstroyexport.
According to Iran’s nuclear officials, Bushehr power plant will reach 40% capacity during a ceremony that will be held on 12 September 2011. It is expected to reach full capacity in November or December 2011.