Unit 6 of China’s Tianwan NPP in Jiangsu province began commercial operation on 3 June, after completing a 100-hour continuous operation test run at full power. The 1080 MWe (net) domestically-designed ACPR1000 pressurised water reactor at Tianwan 6 is China National Nuclear Corporation's (CNNC) 24th reactor in commercial operation, bringing the company's installed generating capacity to 22.509 GWe (gross). Tianwan 6 was connected to the grid on 11 May after which it underwent tests at 30%, 50% and 100% of its generating capacity before beginning a full-power demonstration operating assessment.
This completes the Tianwan Phase III Project comprising units 5 and 6, both ACPR1000 reactors. First safety-related concrete was poured for unit 5 in 2015, with for unit 6 in 2016. Tianwan 5 began commercial operation in September 2020.
The first four units at the site (Phases I and II), which began commercial operation between June 2007 and December 2018, are Gidropress VVER units supplied by Russia, as will be the seventh and eighth (Phase IV), for which a general contract was signed in March 2020. The Tianwan plant is owned and operated by Jiangsu Nuclear Power Corporation, a joint venture between CNNC (50%), China Power Investment Corporation (30%) and Jiangsu Guoxin Group (20%).
Image: Unit 6 of China's Tianwan NPP enters commercial operation (Photo: CNNC)