05/1983 |
Government grants permission to build nuclear reactor |
10/1985 |
Monju construction starts |
05/1991 |
Plant commissioning starts |
17/12/1992 |
Monju starts system start-up test (SST) |
05/04/1994 |
Monju reaches first criticality |
30/06/1995 |
Monju reaches 40% reactor power |
25/08/1995 |
Japan’s Atomic Energy Commission concludes the cancellation of HWR demonstration plant |
29/08/1995 |
Monju first connects to the grid |
10/1995 |
Monju attains 40% rated power |
08/12/1995 |
Monju sodium leak accident (MSLA) |
25/12/1995 |
First Science and Technology Agency (STA) interim report on MSLA |
13/01/1996 |
Shigeo Nishimura commits suicide |
09/02/1996 |
Second STA interim report on MSLA published |
25/04/1996 |
First round table meeting (RTM) on nuclear policy started by STA |
18/12/1996 |
Monju comprehensive safety review (MCSR) started by PNC and STA |
01/01/1997 |
PNC joins WANO |
31/01/1997 |
JAEC sets a provisional policy on nuclear fuel cycle and launched a specialist assembly (SA) on FBR |
20/02/1997 |
STA publishes final report on the MSLA |
11/03/1997 |
Explosion at the bitumen radioactive waste solidification plant in the Tokai reprocessing plant (EBW-TRP) operated by PNC |
08/04/1997 |
A false description is detected in the STA report on the EBW-TRP based on PNC declarations |
11/04/1997 |
STA launches the PNC restructuring review committee (PNC-RRC) and PNC restructuring headquarters |
01/08/1997 |
PNC-RRC publishes final report “Direction of the PNC restructuring” |
28/11/1997 |
Specialist assembly reports the validity of continuation of FBR R&D to JAEC (JAEC approved it three days later) |
02/12/1997 |
PNC-RRC accepts a report on “A basic plan for new organization” from the working group for new organization |
08/12/1997 |
PNC-RRC submits “A basic plan for new organization” to JAEC |
06/02/1998 |
JAEC publishes final “Guidance for PNC restructuring” |
13/05/1998 |
Japanese parliament (Diet) amends PNC law and formally approves PNC transition into the Japan Nuclear Cycle Development Institute (JNC) |
01/10/1998 |
JNC launches with establishment of Tsuruga Head Office (THO) |
15/02/1999 |
Head office of JNC moves from Tokyo to Tokai |
13/05/1999 |
First Tsuruga International Energy Forum (TIEF-1) convenes |
02/10/1999 |
Monju communication square (MC2) public relations operation starts up |
08/12/2000 |
JNC applies for preliminary consent from local government for the Monju plant modifications to prevent sodium leakage |
05/06/2001 |
Fukui prefecture and Tsuruga city gave preliminary consent to JNC for its application for national approval of the Monju plant modification |
06/06/2001 |
JNC applies for national approval of the Monju plant modification |
07/06/2002 |
JAERI and JNC reach agreement in which JNC merges with JAERI |
26/12/2002 |
National approval on the Monju plant modification is granted |
27/01/2003 |
Kanazawa Branch of Nagoya High Court denies the validity of Monju’s national safety approval |
26/11/2004 |
Japan Atomic Energy Agency formed by law passed by Diet |
07/02/2005 |
Fukui prefecture, Tsuruga city give preliminary consent for Monju works |
03/03/2005 |
Preparations for Monju plant modification begin |
03/2005 |
Fukui prefecture launches energy R&D centralization plan |
30/05/2005 |
The Supreme Court overrules the conclusions of the Kanazawa Branch of the Nagoya High Court |
01/09/2005 |
Monju plant modification starts |
01/10/2005 |
JNC is folded into the newly-formed JAEA |
11/10/2005 |
Japan Atomic Energy Commission publishes pro-FBR ‘Framework for Nuclear Energy Policy’ |
09/2006 |
Integrated plant assessment plan for Monju is drawn up |
18/12/2006 |
Modified system function test (MSFT) begins |
23/05/2007 |
Monju plant modification ends |
30/08/2007 |
MSFT ends |
31/08/2007 |
Entire system function test (ESFT) begins |
12/08/2009 |
ESFT ends |
12/2009 |
Safety verification of the long-term suspended facility is completed |
23/02/2010 |
JAEA applies for preliminary consent from local government for Monju system start-up test |
28/04/2010 |
Fukui prefecture and Tsuruga city give preliminary consent to JAEA |
06/05/2010 |
Monju restarts SST |
08/05/2010 |
Monju reaches criticality |