Belarus nuclear power plant (Credit: Belarus Ministry of Energy)Unit 1 of the Belarus nuclear plant, a 1200MW Russian-designed VVER-1200 reactor, has completed a trial run of its turbine, the Ministry of Energy reported on 30 October.

"The first push of the turbine was carried out at a reactor power of 35%. The turbine was idled and the number of revolutions was gradually increased to the design values ​​of 3000 rpm," the press service of the ministry said.

The communications department of the engineering division of Russian state nuclear corporation Rosatom reported that the unit was currently undergoing a step-by-step increase in turbine power up to 40%, and in the coming days, a series of tests would be carried out on equipment and technological systems. "After that, unit 1 will be connected to the grid and will begin to supply the first kilowatt-hours of electricity to the unified energy system of the Republic of Belarus," it said.

Construction of Belarus 1 began in November 2013 and Belarus 2 in April 2014. Start-up of Belarus 1 began on 7 August when the first nuclear fuel assembly was loaded into the reactor vessel. On 11 October, the reactor was brought to the minimum controlled power level (less than 1%). At that stage more than 50 measurements were carried out, which confirmed the compliance of the nuclear-physical characteristics of the reactor installation with the design parameters.

Belarus 1 is scheduled to begin operation in 2021 and unit 2 in 2022.


Photo: Trial turbine operation has been completed at Belarus nuclear power plant (Credit: Belarus Ministry of Energy)